  • 30MWh unit to power a 4MW boiler (proving air to steam conversion)
  • 2MW grid connection
  • 2 Years Time
  • Run distillery 7 days a week charging at night

In 2023, IMANI ONGD was granted £3.6M from the UK Government’s Department of Energy Security and Net Zero to build a full-scale prototype that will decarbonise the distillation process at Annandale Distillery.

Collaboration et montée en compétences lors d’une session de sensibilisation.


We are delivering this project and are on track for the distillery to start producing low-carbon whisky in 2025. En savoir plus about it in the Financial Times here.